The panel ordered Genesis to pay $301,875 – the highest pecuniary penalty it has ever made – after finding it breached the Electricity Industry Participation Code 2010 by fail ...
The gas-powered Unit 5 turbine in the Huntly Power Station. Photo / NZME
The Electricity Authority’s rulings panel has pinged Genesis Energy for infringements of its code dating back to January 2024.
The panel ordered Genesis to pay $301,875 – the highest pecuniary penalty it has ever made – after finding it breached the Electricity Industry Participation Code 2010 by failing to comply with dispatch instructions.
The independent panel, which deals with complaints about breaches of the code, found that Genesis had failed to comply with dispatch instructions for its gas-driven turbine – Unit 5 – at Huntly during two separate periods in January 2024.
Dispatch instructions are the instructions the system operator – Transpower – issues to generators to provide generation.
The Electricity Authority (EA) said compliance with dispatch instructions is critical for:
The EA lodged a formal complaint over the alleged breach with the rulings panel in December 2025.
In 2022, an amendment to the Electricity Industry Act 2010 increased the maximum penalty for code breaches to $2 million.
The panel also ordered Genesis to pay the authority’s costs of $9937.50.