Visayas grid placed under yellow alert on Nov. 16 — NGCP

نشره GMA News · الفلبين منذ 9 س
Visayas grid placed under yellow alert on Nov. 16 — NGCP
GMA News

ملخص مفصل

Power outages may occur as the Visayas grid will be placed under yellow alert from 5 p.m. to 6 p.m. on Monday, November 16, the National Grid Corporation of the Philippines (NGCP)…

Power outages may occur as the Visayas grid will be placed under yellow alert from 5 p.m. to 6 p.m. on Monday, November 16, the National Grid Corporation of the Philippines (NGCP) said.

In an advisory, the NGCP said the grid had an available capacity of 2,774 megawatts (MW), against a peak demand of 2,636 MW.

The yellow alert was declared due to the unavailability of Toledo Power Corp.'s thermal plant.

Therma Visayas Inc.'s Unit 1 was also operating at a derated capacity, while the Cebu Private Power Corp.'s diesel units were unavailable, the grid operator said.

As of November 16, 14 power plants were on forced outage this month, while others had been offline since October (one), September (two), August (two), June (one), 2025 (three), 2024 (one), 2023 (two) and 2021 (one).

Another 21 plants were operating at derated capacities, resulting in a total of 574.4 MW of unavailable capacity, the NGCP added.

A yellow alert is issued when the operating margin is insufficient to meet the transmission grid's contingency requirement.

The Energy Regulatory Commission (ERC) earlier issued 24 show-cause orders against 13 power generation companies over power outages that affected the Visayas and Mindanao.— MCG, GMA News

Follow GMA News Online on Facebook for real-time news and developments in the Philippines and around the world.

مطلع المقال، مقتطف من GMA News. لقراءة المقال كاملًا، افتحه على موقع الناشر.

اقرأ المقال كاملًا على GMA News سجّل الدخول للحفظ

يعرض MarketNews العنوان والملخص كما نشرتهما الوسيلة الإعلامية. المقال الكامل متوفر على موقع الناشر. (www.gmanetwork.com)

يستحق القراءة أيضًا