Work on Doha South Sewage Treatment Plant Project 65% complete

نشره The Peninsula · قطر منذ 8 س
Work on Doha South Sewage Treatment Plant Project 65% complete
Work on Doha South Sewage Treatment Plant Project 65% complete · The Peninsula

ملخص مفصل

Doha, Qatar:Work on Phase 1 of the Doha South Sewage Treatment Plant project is approximately 65% complete, the Public Works Authority, Ashghal, has a...

Doha, Qatar: Work on Phase 1 of the Doha South Sewage Treatment Plant project is approximately 65% complete, the Public Works Authority, Ashghal, has announced as President HE Eng. Mohammed bin Abdulaziz Al Meer, accompanied by several senior officials, visited the project site to review progress, assess the remaining works and discuss the construction schedule.

During the visit, Al Meer reviewed the plant’s main facilities and its technologies for sewage treatment, sludge treatment and energy recovery. The project team briefed him on the construction stages, operational equipment and plans for future expansion. He stressed the importance of adhering to the project schedule and meeting quality and safety requirements to ensure the integration of facilities and their readiness for operation.

President of Ashghal said: “The Doha South Sewage Treatment Plant project, being implemented through a public-private partnership (PPP) with a total investment of QAR 6.3 billion, including approximately QAR 2.3 billion in foreign investment, represents a significant milestone in strengthening the private sector’s role in major national infrastructure projects.”

The project will develop an integrated sewage system that will serve more than 300,000 people in Southern Qatar in its first phase. The plant will produce treated water that meets international standards, helping improve water resource efficiency and supporting Qatar’s efforts to promote environmental sustainability and mitigate the effects of climate change.

It is worth noting that the Doha South Sewage Treatment Plant project (Phase 1) is the first sewage infrastructure project in Qatar to be implemented under a public-private partnership (PPP) model.

The partnership agreement covers design, financing and construction, as well as the operation and maintenance of the plant by the project developer for 25 years.

The project gives local companies opportunities to supply materials and equipment and provide services during…

Abdulaz…

مطلع المقال، مقتطف من The Peninsula. لقراءة المقال كاملًا، افتحه على موقع الناشر.

اقرأ المقال كاملًا على The Peninsula سجّل الدخول للحفظ

يعرض MarketNews العنوان والملخص كما نشرتهما الوسيلة الإعلامية. المقال الكامل متوفر على موقع الناشر. (thepeninsulaqatar.com)

يستحق القراءة أيضًا