Snowy 2.0 “as complex as you get” before building nuclear, says CEO – “we didn’t recognise it”

نشره RenewEconomy · أستراليا منذ 13 س
Snowy Hydro CEO Dennis Barnes during Senate Estimates at Parliament House in Canberra in October 2023. (AAP Image/Mick Tsikas)
Snowy Hydro CEO Dennis Barnes during Senate Estimates at Parliament House in Canberra in October 2023. (AAP Image/Mick Tsikas) · RenewEconomy

ملخص مفصل

Snowy Hydro CEO and CCO on the three big mistakes behind Snowy 2.0's budget blowout – and how its tracking now. Plus, why the utility is the "most interesting" in the energy transition.

The CEO of Snowy Hydro says one of the biggest mistakes the government-owned utility made with its huge and now massively over-budget pumped hydro project was to drastically underestimate the level of complexity involved in building a 2,200 megawatt power station around 800 metres underground.

But Dennis Barnes, who appears on Renew Economy’s latest Energy Insiders podcast alongside chief commercial officer Gordon Wymer, says the “complex as hell” Snowy 2.0 build is back hitting critical milestones, including a concrete-pour before Christmas, and that much of the geological risk is now behind it.

Barnes joined Snowy Hydro in February 2023, when the potential scale of the beleaguered project’s cost blowouts and delivery delays were only just starting reveal themselves to the Albanese Labor government, which had come into power the previous May.

By that time, the project that had its start under the Turnbull Coalition government was already running 12-18 months behind schedule and its budget had more than doubled to $5.8 billion. It had also had one of its major contractors go bankrupt, and was in the midst of a run of protracted tunnelling issues.

By August of 2023, a major project review and reset saw Snowy 2.0’s delivery date pushed out to December 2028 – seven years later than originally forecast – and the bill for development revised upwards to somewhere around $12 billion.

Last month, following a third project reassessment more than a year in the making, Snowy Hydro conceded that costs were now expected to double again, to $22-25 billion, and its full commissioning be delayed another year to the end of 2029.

The latest Snowy 2.0 “reset” has been met with a great deal of criticism and ‘I told you so’s, and plenty of calls for the project to be abandoned, before it winds up delivering yet another doubling in costs.

But Barnes says Snowy 2.0 is now in a “pretty strong position,” and Snowy Hydro, itself, is much more in control of the logistics and risks of the sprawling…

“…

مطلع المقال، مقتطف من RenewEconomy. لقراءة المقال كاملًا، افتحه على موقع الناشر.

اقرأ المقال كاملًا على RenewEconomy سجّل الدخول للحفظ

يعرض MarketNews العنوان والملخص كما نشرتهما الوسيلة الإعلامية. المقال الكامل متوفر على موقع الناشر. (reneweconomy.com.au)

يستحق القراءة أيضًا